Zara Aavaas-3
Price on request
HRERA filings carry no unit pricing — we confirm the current band with the developer.
RERA registered — GGM/464/196/2021/32 DATED 27.07.2021, valid to 31/12/2026
- Land area
- 2.28 acres
- Declared completion
- Jul 2024
- Project cost
- ₹78.09 Cr
Delivery status
REP-I Part C- Declared completion
- Jul 2024
- Status
- Overdue
- Layout approved
- 11-11-2020
- Building plan
- 11-11-2020
The completion date the promoter filed has already passed. Treat the handover date as unmet until a fresh quarterly progress report says otherwise.
Approvals & compliance
REP-I Part EStatutory approvals: 6 obtained, 0 pending
- Roads
- ALREADY CONNECTED · approved
- Electricity
- DHBVNL,GURUGRAM · approved
- Water Supply
- W/S,DIVISION, GMDA, GURUGRAM · approved
- Sewage Disposal
- SEW,DIV,GMDA, GURUGRAM · approved
- Storm Water Drainage
- HSVP · approved
Agency sign-off for external connections stands at 5 of 5 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.
Amenities
REP-I Part C- Elect Sub Station
- Electricity Supply System
- Internal Roads and Pavements
- Misc
- Parking
- Playgrounds and Parks
- Rain Water Harvesting
- Renewable Energy System
- Security and Fire Fighting
- Sewage Treatment & Garbage Disposal
- Storm Water Drainage
- STP
- Street Lighting
- Ugt
- Water Supply System
These are the facilities the promoter costed into its service plan estimates — not a marketing list.
Licence & legal
REP-I Part B- RERA registration
- GGM/464/196/2021/32 DATED 27.07.2021
- Valid up to
- 31/12/2026
- Town planning licence
- 72 of 2019
- Promoter is licensee
- Yes
- Promoter CIN
- U45201DL2004PTC125145
- Permissible FAR
- 2.25%
- Proposed FAR
- 2.28%
- Litigation declared
- No
About this project
Zara Aavaas-3 is a group housing project by Perfect Buidwell Pvt Ltd in Sector 104, Gurugram, registered with the Haryana Real Estate Regulatory Authority under GGM/464/196/2021/32 DATED 27.07.2021. The promoter has declared a project area of 2.28 acres. All 6 statutory approvals listed in the filing are recorded as obtained. Agency sign-off for external services stands at 5 of 5 — covering roads, water, electricity, sewage and storm-water drainage. The completion date filed with the authority was Jul 2024 — that date has now passed. It is developed on town-planning licence 72 of 2019. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.
Location
REP-I Part AGurugram, Sector 104
Open in Google MapsEvery figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.