Urban Homes-ii Extension
Price on request
HRERA filings carry no unit pricing — we confirm the current band with the developer.
RERA registered — GGM/412/144/2020/28 DATED 28.09.2020, valid to 15/11/2023
- Land area
- 1.5 acres
- Declared completion
- Nov 2023
- Project cost
- ₹42.50 Cr
Delivery status
REP-I Part C- Declared completion
- Nov 2023
- Status
- Overdue
- Layout approved
- 15-06-2020
- Building plan
- 15-06-2020
The completion date the promoter filed has already passed. Treat the handover date as unmet until a fresh quarterly progress report says otherwise.
Approvals & compliance
REP-I Part EStatutory approvals: 5 obtained, 2 pending
- Roads
- NA · not taken
- Electricity
- DHBVN · approved
- Water Supply
- HSVP · approved
- Sewage Disposal
- HSVP · approved
- Storm Water Drainage
- HSVP · approved
Agency sign-off for external connections stands at 4 of 5 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.
Amenities
REP-I Part C- Internal Roads and Pavements
- Playgrounds and Parks
- Service and Resurfacing of Road
- Sewage Treatment & Garbage Disposal
- Storm Water Drainage
- Street Lighting
- Water Supply System
These are the facilities the promoter costed into its service plan estimates — not a marketing list.
Licence & legal
REP-I Part B- RERA registration
- GGM/412/144/2020/28 DATED 28.09.2020
- Valid up to
- 15/11/2023
- Town planning licence
- 78 of 2018
- Licensee on record
- Gallium Propbuild P Ltd
- Promoter is licensee
- No
- Promoter CIN
- U45400HR2008PTC038509
- Permissible FAR
- 2.25%
- Proposed FAR
- 2.25%
- Litigation declared
- No
The land licence is held by Gallium Propbuild P Ltd, not by the promoter. That is normal for a collaboration project, but it means the agreement chain runs through two entities — check both before signing.
About this project
Urban Homes-ii Extension is a group housing project by Pyramid Infratech Private Limited in Sector 86, Gurugram, registered with the Haryana Real Estate Regulatory Authority under GGM/412/144/2020/28 DATED 28.09.2020. The promoter has declared a project area of 1.5 acres. 5 statutory approvals are recorded as obtained and 2 as still pending. Agency sign-off for external services stands at 4 of 5 — covering roads, water, electricity, sewage and storm-water drainage. The completion date filed with the authority was Nov 2023 — that date has now passed. It is developed on town-planning licence 78 of 2018. The land licence is held by Gallium Propbuild P Ltd, with the promoter developing under a collaboration arrangement. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.
Location
REP-I Part AGurugram, Sector 86
Open in Google MapsEvery figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.