RERA registered — GGM/834/566/2024/61 DATED 12.08.2024, valid to 31/03/2032
- Land area
- 9.169 acres
- Declared completion
- Dec 2031
- Project cost
- ₹1111.44 Cr
Delivery status
REP-I Part C- Declared completion
- Dec 2031
- Status
- On schedule
- Layout approved
- 16-07-2024
- Building plan
- 16-07-2024
Approvals & compliance
REP-I Part EStatutory approvals: 3 obtained, 0 pending
- Roads
- GMDA (ALREADY CONNECTED) · not taken
- Electricity
- GMDA (ASSURANCE TAKEN) · not taken
- Water Supply
- GMDA (ASSURANCE TAKEN) · not taken
- Sewage Disposal
- GMDA (ASSURANCE TAKEN) · not taken
- Storm Water Drainage
- GMDA (ASSURANCE TAKEN) · not taken
Agency sign-off for external connections stands at 0 of 5 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.
Amenities
REP-I Part C- Construction of Circulation Road
- Electricity Supply System
- Internal Roads and Pavements
- Playgrounds and Parks
- Rain Water Harvesting
- Renewable Energy System
- Security and Fire Fighting
- Sewage Treatment & Garbage Disposal
- Storm Water Drainage
- STP
- Street Lighting
- Underground Water Tank
- Water Supply System
These are the facilities the promoter costed into its service plan estimates — not a marketing list.
Licence & legal
REP-I Part B- RERA registration
- GGM/834/566/2024/61 DATED 12.08.2024
- Valid up to
- 31/03/2032
- Town planning licence
- 21 of 2024
- Licensee on record
- 1. Amit Yadav S/O Chattar Singh
- Promoter is licensee
- No
- Promoter CIN
- U7010DL2005PTC144086
- Permissible FAR
- 4.11%
- Proposed FAR
- 4.08%
The land licence is held by 1. Amit Yadav S/O Chattar Singh, not by the promoter. That is normal for a collaboration project, but it means the agreement chain runs through two entities — check both before signing.
About this project
Tulip Crimson is a group housing project by Tulip Infratech Pvt. Ltd in Sector 70, Gurugram, registered with the Haryana Real Estate Regulatory Authority under GGM/834/566/2024/61 DATED 12.08.2024. The promoter has declared a project area of 9.169 acres. All 3 statutory approvals listed in the filing are recorded as obtained. Agency sign-off for external services stands at 0 of 5 — covering roads, water, electricity, sewage and storm-water drainage. The filed completion date is Dec 2031. It is developed on town-planning licence 21 of 2024. The land licence is held by 1. Amit Yadav S/O Chattar Singh, with the promoter developing under a collaboration arrangement. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.
Location
REP-I Part AGurugram, Sector 70
Open in Google MapsEvery figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.
You May Also Like