Signature Global City 92-(ii)
Price on request
HRERA filings carry no unit pricing — we confirm the current band with the developer.
RERA registered — GGM/666/398/2023/10 DATED 13.01.2023, valid to 29/03/2027
- Land area
- 2.494 acres
- Declared completion
- Mar 2025
- Project cost
- ₹139.43 Cr
Delivery status
REP-I Part C- Declared completion
- Mar 2025
- Status
- Overdue
- Layout approved
- 28-06-2022
- Building plan
- 27-10-2022
The completion date the promoter filed has already passed. Treat the handover date as unmet until a fresh quarterly progress report says otherwise.
Approvals & compliance
REP-I Part EStatutory approvals: 6 obtained, 1 pending
- Roads
- GMDA · approved
- Electricity
- DHBVN · approved
- Water Supply
- GMDA · approved
- Sewage Disposal
- GMDA · approved
- Storm Water Drainage
- NA · not taken
Agency sign-off for external connections stands at 4 of 5 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.
Licence & legal
REP-I Part B- RERA registration
- GGM/666/398/2023/10 DATED 13.01.2023
- Valid up to
- 29/03/2027
- Town planning licence
- 12 of 2021
- Licensee on record
- Ramprastha Estates Private Limited
- Promoter is licensee
- No
- Promoter CIN
- U70100DL2013PTC247676
- Permissible FAR
- 2.64%
- Proposed FAR
- 2.64%
- Litigation declared
- No
The land licence is held by Ramprastha Estates Private Limited, not by the promoter. That is normal for a collaboration project, but it means the agreement chain runs through two entities — check both before signing.
About this project
Signature Global City 92-(ii) is a group housing project by Signature Infrabuild Pvt. Ltd. in Sector 92, Gurugram, registered with the Haryana Real Estate Regulatory Authority under GGM/666/398/2023/10 DATED 13.01.2023. The promoter has declared a project area of 2.494 acres. 6 statutory approvals are recorded as obtained and 1 as still pending. Agency sign-off for external services stands at 4 of 5 — covering roads, water, electricity, sewage and storm-water drainage. The completion date filed with the authority was Mar 2025 — that date has now passed. It is developed on town-planning licence 12 of 2021. The land licence is held by Ramprastha Estates Private Limited, with the promoter developing under a collaboration arrangement. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.
Location
REP-I Part AGurugram, Sector 92
Open in Google MapsEvery figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.