Pyramid Pride
Price on request
HRERA filings carry no unit pricing — we confirm the current band with the developer.
RERA registered — GGM/332/64/2019/26 DATED 24.05.2019, valid to 24/02/2024
- Land area
- 5 acres
- Declared completion
- Feb 2024
- Project cost
- ₹155.65 Cr
Delivery status
REP-I Part C- Declared completion
- Feb 2024
- Status
- Overdue
- Layout approved
- 08-05-2019
- Building plan
- 08-05-2019
The completion date the promoter filed has already passed. Treat the handover date as unmet until a fresh quarterly progress report says otherwise.
Approvals & compliance
REP-I Part EStatutory approvals: 3 obtained, 1 pending
- Roads
- ALREADY CONNECTED · not taken
- Electricity
- DHBVN · approved
- Water Supply
- HSVP · approved
- Sewage Disposal
- HSVP · approved
- Storm Water Drainage
- HSVP · approved
Agency sign-off for external connections stands at 4 of 5 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.
Amenities
REP-I Part C- Electrical Sub Station
- Electricity Supply System
- Internal Roads and Pavements
- Parking
- Playgrounds and Parks
- Rain Water Harvesting
- Renewable Energy System
- Security and Fire Fighting
- Sewage Treatment & Garbage Disposal
- Storm Water Drainage
- STP
- Street Lighting
- Underground Water Tank
- Water Supply System
These are the facilities the promoter costed into its service plan estimates — not a marketing list.
Licence & legal
REP-I Part B- RERA registration
- GGM/332/64/2019/26 DATED 24.05.2019
- Valid up to
- 24/02/2024
- Town planning licence
- 26 of 2019
- Licensee on record
- Hemadri Real Estate Developers Private Limited
- Promoter is licensee
- No
- Promoter CIN
- U45400HR2008PTC038509
- Permissible FAR
- 2.25%
- Proposed FAR
- 2.25%
- Litigation declared
- No
The land licence is held by Hemadri Real Estate Developers Private Limited, not by the promoter. That is normal for a collaboration project, but it means the agreement chain runs through two entities — check both before signing.
About this project
Pyramid Pride is a group housing project by Pyramid Infratech Pvt. Ltd. in Sector 76, Gurugram, registered with the Haryana Real Estate Regulatory Authority under GGM/332/64/2019/26 DATED 24.05.2019. The promoter has declared a project area of 5 acres. 3 statutory approvals are recorded as obtained and 1 as still pending. Agency sign-off for external services stands at 4 of 5 — covering roads, water, electricity, sewage and storm-water drainage. The completion date filed with the authority was Feb 2024 — that date has now passed. It is developed on town-planning licence 26 of 2019. The land licence is held by Hemadri Real Estate Developers Private Limited, with the promoter developing under a collaboration arrangement. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.
Location
REP-I Part AGurugram, Sector 76
Open in Google MapsEvery figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.
You May Also Like