Ashiana Anmol Plaza Phase I
Price on request
HRERA filings carry no unit pricing — we confirm the current band with the developer.
RERA registered — GGM/363/95/2019/57 DATED 03.10.2019, valid to 31/10/2019
- Land area
- 0.339 acres
- Declared completion
- Jan 2019
- Project cost
- ₹2.58 Cr
Delivery status
REP-I Part C- Declared completion
- Jan 2019
- Status
- Overdue
- Layout approved
- 30-01-2015
- Building plan
- 30-01-2015
The completion date the promoter filed has already passed. Treat the handover date as unmet until a fresh quarterly progress report says otherwise.
Approvals & compliance
REP-I Part EStatutory approvals: 7 obtained, 0 pending
- Roads
- NA · not taken
- Electricity
- DHBVN · approved
- Water Supply
- HUDA · approved
- Sewage Disposal
- HUDA · approved
- Storm Water Drainage
- NA · not taken
Agency sign-off for external connections stands at 3 of 5 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.
Amenities
REP-I Part C- Electricity Supply System
- Internal Roads and Pavements
- Security and Fire Fighting
- Sewage Treatment & Garbage Disposal
- Storm Water Drainage
- Street Lighting
- Water Supply System
These are the facilities the promoter costed into its service plan estimates — not a marketing list.
Licence & legal
REP-I Part B- RERA registration
- GGM/363/95/2019/57 DATED 03.10.2019
- Valid up to
- 31/10/2019
- Town planning licence
- 20 of 2014
- Licensee on record
- Universe Heights (India)Pvt. Ltd.
- Promoter is licensee
- No
- Promoter CIN
- L70109WB1986PLC040864
- Permissible FAR
- 1.75%
- Proposed FAR
- 1.74%
- Litigation declared
- Yes
The land licence is held by Universe Heights (India)Pvt. Ltd., not by the promoter. That is normal for a collaboration project, but it means the agreement chain runs through two entities — check both before signing.
About this project
Ashiana Anmol Plaza Phase I is a group housing project by Ashiana Housing Limited in Sector 33, Gurugram, registered with the Haryana Real Estate Regulatory Authority under GGM/363/95/2019/57 DATED 03.10.2019. The promoter has declared a project area of 0.339 acres. All 7 statutory approvals listed in the filing are recorded as obtained. Agency sign-off for external services stands at 3 of 5 — covering roads, water, electricity, sewage and storm-water drainage. The completion date filed with the authority was Jan 2019 — that date has now passed. It is developed on town-planning licence 20 of 2014. The land licence is held by Universe Heights (India)Pvt. Ltd., with the promoter developing under a collaboration arrangement. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.
Location
REP-I Part AGurugram, Sector 33
Open in Google MapsEvery figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.