Zara Rossa
Price on request
HRERA filings carry no unit pricing — we confirm the current band with the developer.
RERA registered — 82 OF 2017 DATED 23.08.2017, valid to 30/06/2024
- Land area
- 5.006 acres
- Declared completion
- Apr 2023
- Project cost
- ₹165.61 Cr
Delivery status
REP-I Part C- Declared completion
- Apr 2023
- Status
- Overdue
- Layout approved
- 03-05-2017
- Building plan
- 16-10-2017
The completion date the promoter filed has already passed. Treat the handover date as unmet until a fresh quarterly progress report says otherwise.
Approvals & compliance
REP-I Part EStatutory approvals: 6 obtained, 1 pending
- Electricity
- DHBVN(MEMO NO-99 DATED 21.09.2016) · approved
- Water Supply
- HUDA(MEMO NO-159240 DATED 25.08.2017) · approved
- Sewage Disposal
- HUDA(MEMO NO-159239 DATED 25.08.2017) · approved
- Storm Water Drainage
- GMDA(MEMO NO-GMDA/DRAINAGE/2021/129 DATED 24.02.2021) · approved
Agency sign-off for external connections stands at 4 of 4 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.
Amenities
REP-I Part C- Electricity Supply System
- Internal Roads and Pavements
- Playgrounds and Parks
- Renewable Energy System
- Security and Fire Fighting
- Sewage Treatment & Garbage Disposal
- Storm Water Drainage
- Street Lighting
- Water Supply System
These are the facilities the promoter costed into its service plan estimates — not a marketing list.
Licence & legal
REP-I Part B- RERA registration
- 82 OF 2017 DATED 23.08.2017
- Valid up to
- 30/06/2024
- Town planning licence
- 7 of 2016
- Promoter is licensee
- Yes
- Promoter CIN
- U70102DL2013PTC257689
- Permissible FAR
- 228%
- Proposed FAR
- 228%
About this project
Zara Rossa is a group housing project by Deluris Buildtech India Private Limited in Sector 112, Gurugram, registered with the Haryana Real Estate Regulatory Authority under 82 OF 2017 DATED 23.08.2017. The promoter has declared a project area of 5.006 acres. 6 statutory approvals are recorded as obtained and 1 as still pending. Agency sign-off for external services stands at 4 of 4 — covering roads, water, electricity, sewage and storm-water drainage. The completion date filed with the authority was Apr 2023 — that date has now passed. It is developed on town-planning licence 7 of 2016. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.
Location
REP-I Part AGurugram, Sector 112
Open in Google MapsEvery figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.